PennDOT's Scheduled Roadwork for the Week March15, 2019 through March 22, 2019

03/15/2019

Dunmore – The following work is scheduled for this week throughout Northeastern Pennsylvania.  Anyone wishing to sign up for PennDOT Travel Advisories can do so by subscribing  to PennDOT news in Lackawanna, Luzerne, Pike, Susquehanna, Wayne, and Wyoming counties at www.penndot.gov/District4  Follow/like PennDOT on Twitter at 511PANortheast and Facebook at Pennsylvania Department of Transportation (PennDOT).

Please note all work depends on weather conditions.

Interstate 84

Short Term

I-84 E- -Westfall Township-Lane Restriction-Crack Seal-18-Mar-19-21-Mar-19-7:30 AM to 2:30 PM.

I-84- -Salem-Single Lane-Brushing-3/18/2019-3/22/2019-7 AM to 3 PM

Long Term

Exit 30 (Blooming Grove/ Porters Lake) to Exit 46 (Milford): The project is currently completed for the winter. The project will continue in the spring of 2019. Crews are working on roadway and bridge reconstruction work between these exits. Three westbound structures and approximately 3.5 miles of westbound interstate roadway are to be completed during this construction season.  No permanent lane closures will be allowed during the winter months. The project is scheduled to be completed by October 2019.
 
Lackawanna County

Long Term

SR 307 Bridge over I-81 (Moosic St., Scranton)The project is currently shut down for the winter and will resume in the spring of 2019 and no additional closing of River St off ramp will be needed.  

Luzerne County:

Luzerne County police departments will be conducting DUI enforcement, this weekend for the Saint Patrick’s holiday. The police departments are Jackson Township, Dallas Township, Hazleton City, West Hazleton, Fairview Township, Wright Township, Hughstown  Boro and Butler Township.

SR 4024 in Fairmount will be closed with detour starting on Monday, March 4 until the end of the summer for a bridge deck repair.  Detour will be posted. 

UPDATE: A recent inspection has shown that the pipe that carries the creek under SR 92 has sustained damage due to the water main break & collapse of the road. As a result State Route 92 will be closed for a few weeks.  State Route 92 is closed in Exeter due to a water main break under the road.  Large portions of the road have been washed away, so there is no anticipated day for reopening at this time.  Crews are on scene and will be establishing a detour shortly.

Long Term

SR 309 Northbound from River St., SR 2004,at Exit #3. The on ramp bridge from River St. (SR 2004) to the North Cross Valley Expressway (SR 309 NB) was open to traffic on Jan. 6, 2019.

SR 309 North Cross Valley will have a lane restriction on Sunday, March 24 from 7 PM to Monday, March 25 at 6 AM for the setting of the  barriers for the bridge project near Exit 6, Luzerne.  Work will take place between Exits 4 and 6. Please note that two lanes will be open north and south during the construction.  Completion will be November 2019.

Up Coming Work-Phase 2
The off ramp bridge from the North Cross Valley Expressway (SR 309 SB) to River St. (SR 2004) is scheduled to be closed early spring 2019 through Summer of 2020. The off ramp bridge deck and parapets will be removed and replaced.  The beams and girders will be inspected and painted.

A signed detour will be in place Spring 2019 for the duration of the off ramp construction. The signed River St. detour will follow the North Cross Valley Expressway south (SR 309 south) to Wilkes-Barre Boulevard at Exit 2 where temporary signals have been installed. A left turn on the green signal may be made onto Wilkes-Barre Boulevard northbound. Follow the River St. detour signs to the on ramp of the North Cross Valley Expressway to SR 309 north.  Vehicles can access River St., SR 2004, from SR 309 NB at Exit #3 via the off ramp, Ramp D-D.

SR 2045, (South Main Road), bridge closed on Thursday, December 27, 2018 due to an emergency bridge repair. The project will include replacing a pipe that has deteriorated underneath and has left the bridge unsafe. The bridge tentative completion date for this project is late September of 2019. A detour will be placed during this time.  The detour will be Nuangola Rd (2042) to Church Rd (2047) and back to South Main Rd (2045).

SR 3034 (Butler Ave) Conyngham: PennDOT has closed the bridge on SR 3034 (Butler Ave) Conyngham after a routine inspection.  The bridge will be replaced starting in the spring of 2020.   A detour is in place.

South Valley Parkway Project
The Prospect Street roundabout is being re-engineered due to unforeseen conditions.  The Department did not want to inconvenience the public, so the area was opened up.  Once the re-engineering is completed,  construction of Prospect Street will resume.   The Prospect Roundabout will be not be completed in 2018, but will opened during winter months, and closed again in late

Pike County

Short Term

SR 6- -Shohola Township-Lane Restriction-Patching  potholes /Brush & Tree removal/ day lighting signs various rds with in  the county-21-Mar-19-22-Mar-19-7:30 AM to 2:30 PM

SR 739- -Delaware Township-Lane Restriction-Mechanized Brushing, manual Brush cutting-18-Mar-19-22-Mar-19-7:30 AM to 2:30 PM

SR 1003-Rowland Rd -Lackawaxen Township-Lane Restriction-Patching potholes/brush & tree removal/day lighting signs -18-Mar-19-20-Mar-19-7:30 AM to 2:30 PM

SR 2001-Milford Rd -Dingmans Ferry -Lane Restriction-Crack seal-22-Mar-19-22-Mar-19-7:30 AM to 2:30 PM

SR 4004-Blooming Grove Rd-Blooming Grove Township-Lane Restriction-Crack Seal/Patching various potholes /Brush & Tree removal/ day lighting signs various roads within the county-18-Mar-19-22-Mar-19-7:30 AM to 2:30 PM
 
-Various Roads - -Lane Restriction-Pot Hole Patching Throughout the County - - -

Susquehanna County

Short Term

Various--Great Bend TWP-Lane Restrictions-Pot Hole Patching-Monday, March 3/18/2019-Friday March 03/22/2019-7AM to 3PM

Various--Thompson-Lane Restrictions-Brushing-Monday, March 3/18/2019-Friday March 03/22/2019-7AM to 3PM

Various--Herrick TWP-Lane Restrictions-Pot Hole Patching-Monday, March 3/18/2019-Friday March 03/22/2019-7AM to 3PM

Various--Lenox TWP-Lane Restrictions-Pot Hole Patching-Monday, March 3/18/2019-Friday March 03/22/2019-7AM to 3PM

Long Term

SR 3037 (Rush Twp.)- There is a bridge closure from the intersection of SR 367 to the intersection of SR 267 in Rush Township. The bridge is closed due to pier deficiency. A detour is posted.          .

Wayne County

Short Term

Various Routes- -Patching-3/18/2019-3/22/2019-7 AM to 3 PM

Various Routes-Single Lane-Patching-3/18/2019-3/22/2019-7 AM to 3 PM

SR 6-Texas Palmyra Hwy-Texas-Single Lane-Patching-3/18/2019-3/22/2019-7 AM to 3 PM

SR 191-Hancock Highway-Lebanon/Damascus-Single Lane-Drainage-3/18/2019-3/22/2019-7 AM to 3 PM

SR 196-Easton Tpk-Lake -Single Lane-Brushing/Ditching-3/18/2019-3/22/2019-7 AM to 3 PM

SR 652-Beachlake Hwy-Berlin -Single Lane-Patching-3/18/2019-3/22/2019-7 AM to 3 PM

SR 1001-Cliff Street-Honesdale Borough -Single Lane-Crack Sealing-3/18/2019-3/22/2019-7 AM to 3 PM

SR 1006-Peggy Runway-Berlin -Single Lane-Pipe Replacement-3/18/2019-3/22/2019-7 AM to 3 PM

SR 1023-Pine Mill Rd-Lebanon/Manchester-Single Lane-Brushing-3/18/2019-3/22/2019-7 AM to 3 PM

SR 3005-Forks Bridge Rd-Salem/Lake-Single Lane-Ditching -3/18/2019-3/22/2019-7 AM to 3 PM

SR 3019-Maple Wood Rd-Salem / Lake-Single Lane-Ditching -3/18/2019-3/22/2019-7 AM to 3 PM

SR 3031-Terrace St-Honesdale Borough -Single Lane-Crack Sealing-3/18/2019-3/22/2019-7 AM to 3 PM

SR 4001-Elk Lake Dr.-Canaan/Clinton-Single Lane-Drainage/Brush cutting-3/18/2019-3/22/2019-7 AM to 3 PM

SR 4004-White Oak-Clinton -Single Lane-Drainage-3/18/2019-3/22/2019-7 AM to 3 PM

SR 4037-Scott Center Rd-Preston-Single Lane-Drainage-3/18/2019-3/22/2019-7 AM to 3 PM
 
Wyoming County

Short Term

--Multiple Locations-Short term lane closure-Cold Patching-Monday (3/18)-Friday (3/22)-7:00 AM to 3:00 PM

SR 29--Eaton and Monroe Township-Short term lane closure-Ditch Cleaning-Monday (3/18)-Friday (3/22)-7:00 AM to 3:00 PM

SR 187--North Branch Township-Short term lane closure-Ditching and Wash out repair-Monday (3/18)-Friday (3/22)-7:00 AM to 3:00 PM

SR 292--North Moreland Township-Short term lane closure-Driveway Pipe installation and Ditching-Monday (3/18)-Friday (3/22)-7:00 AM to 3:00 PM

SR 1002--Tunkhannock Township-Short term lane closure-Ditching/Wash out repair/brushing-Monday (3/18)-Friday (3/22)-7:00 AM to 3:00 PM

SR 4008--Washington Township-Short term lane closure-slide repair/pipe replacement-Monday (3/18)-Friday (3/22)-7:00 AM to 3:00 PM

MEDIA CONTACT: Michael S. Taluto, 570-963-3502
 

Source: PennDOT District 4