I-81 Susquehanna Project

Project Description

The I-81 Susquehanna Project is a nine-mile stretch of reconstruction and repair work along I-81 from New Milford Borough to the New York border. Work includes the replacement of the dual bridges over the Susquehanna River between Hallstead Borough and Great Bend Borough, which were built in 1961 and rehabilitated in 1979, 1993 and 2006. Combined, the bridges carry about 27,000 vehicles per day, approximately 41 percent of which is truck traffic. The combined daily traffic is expected to more than double by 2045 to around 55,000.

The purpose of the I-81 Susquehanna Project is to address aging pavement and infrastructure along I-81 including the bridge over the Susquehanna River, and to lengthen on and off ramps to meet current interstate design standards and improve safety.

The project is intended to address the following needs:

  • Aging infrastructure. Most of the pavement in the corridor is nearly 60 years old, and the Susquehanna River bridges are approaching the end of their serviceable lifespan.
  • Outdated interchange designs. The on and off ramps at the interchanges throughout the corridor do not meet current and future traffic design standards.
  • Outdated construction methods. All structures on the corridor were constructed with reinforced concrete that contains more chloride ion content than modern standards allow. While safe, this type of reinforced concrete has a shorter lifespan than most reinforced concrete used today.
  • Drainage concerns. The storm system built into much of the corridor has exceeded its serviceable lifespan.

The project involves a number of construction activities, including:

  • Repaving all roadway in the corridor
  • Replacing five dual bridge structures, including the bridges over the Susquehanna River and one overpass structure
  • Replacing the drainage system
  • Replacing all guiderails, barriers and signage in the corridor
  • Construction work on Susquehanna Street, PA-171 and PA-1029 (Randolph Road)

Through the National Environmental Policy Act (NEPA) environmental review process, the I-81 Susquehanna Project was approved as a Categorical Exclusion (CE) in 2017, and the project team was allowed to move forward with final design, right-of-way acquisition and construction.

PennDOT is reevaluating the CE for this project because it is one of several projects being evaluated as a candidate for bridge tolling. A bridge toll is a fee that drivers pay when passing a specific location, often by using a service like E-ZPass. The cost to construct the project is estimated at between $175 and $200 million. The funds received from the bridge toll will go back to the I-81 Susquehanna Project to pay for construction, maintenance and operation. The proposed bridge toll for this project would be located at the Susquehanna River bridge between Hallstead and Great Bend.

As part of the environmental reevaluation, PennDOT is analyzing how bridge tolling may impact local communities and how alternate routes drivers could take to avoid the toll may impact local traffic and roadways. When studies are completed in Spring 2021, we will present our findings for public review and comment in a virtual public meeting. During the meeting, the team will also share project details, such as engineering design, environmental impacts, construction schedule and maintenance and protection of traffic during construction.

The project is currently in final design, and construction is anticipated to begin between 2023 and 2025.

To stay informed or to be added to the project mailing list, please complete the form at the bottom of this page. You may also submit your comments and feedback by using this form.

PennDOT Pathways Major Bridge P3 Initiative

 Content Editor ‭[3]‬


On November 12, 2020, PennDOT received the Pennsylvania P3 Board's approval of the Major Bridge P3 Initiative, which allows the use of the P3 delivery model for bridges in need of replacement or rehabilitation, and to consider tolls at these locations. P3, which stands for Public-Private Partnership, is a cooperative arrangement between two or more public and private sectors that involves government and businesses working together to complete a project that will serve the public. PennDOT's P3 Office develops innovative project delivery and financing models for a wide array of initiatives that are designed to strengthen and improve the state's transportation network.

Through the P3 model, PennDOT can leverage private investment to rebuild critical bridges during a period with historically low interest rates and a favorable labor market. This initiative can provide a dedicated source of revenue for these infrastructure improvements and could create significant savings over the life of the program while ensuring the vitality of the state's transportation system and economy.

Bridge tolling can provide the funds to repair or replace these costly bridges without using PennDOT's current funding, which in turn allows those funds to be used for other roadway maintenance, operations, and improvements. Tolling would be all electronic and collected by using E-ZPass or license plate billing. The funds received from the toll would go back to the bridge where the toll is collected to pay for the construction, maintenance, and operation of that bridge.

The candidate bridges being considered for tolling through the Major Bridge P3 Initiative were selected based on the following criteria:

  • interstate location
  • structure of substantial size and cost to replace or rehabilitate
  • warrants timely attention
  • maintains geographic balance
  • does not impact just one region or corridor
  • ability to begin construction in 2-4 years for the near-term benefit

In the coming years, PennDOT will evaluate these candidate bridges through individual environmental documents being prepared or re-evaluated for each bridge. More information on each individual bridge project, and when the public will have an opportunity to engage on those projects, can be found at www.penndot.gov/funding.

To support PennDOT Pathways, an alternative funding Planning and Environmental Linkages (PEL) study is underway to identify near- and long-term funding solutions and establish a methodology for their evaluation. One of the early findings of the PEL study is that tolling of major bridges in need of replacement or rehabilitation appears to be a viable near-term solution. To advance this funding alternative, PennDOT is pursuing the first initiative of the PennDOT Pathways Program: the Major Bridge P3 Initiative.

PennDOT Pathways is a program to identify and implement alternative funding solutions for Pennsylvania's transportation network. As Pennsylvania's mobility needs have grown, the amount of funding required to support our highway and bridges has continued to increase. PennDOT's current highway and bridge budget is about $6.9 billion per year. Although that's a lot of money, it's less than half of the $15 billion needed to keep Pennsylvania's highways and bridges in a state of good repair and address major bottlenecks on our roadway network. Much of PennDOT's current funding comes from gas taxes and driver and vehicle fees. While this model worked well in the past, circumstances today have made it unsustainable. With PennDOT Pathways, we're looking for reliable, future-focused funding solutions that will meet our growing needs while serving our communities. The PennDOT Pathways PEL study will evaluate additional alternative funding solutions and will be available for public comment in the spring of2021.