- Scope: Resurfacing (4.0 Miles), Guide Rail, and Drainage Upgrades (to Maryland State Line)
- Construction Timeframe: July 2021 to November 2022
- Traffic Control: Long Term Traffic Control, Phased Setups, & Detour
- Detour length: 1.6 Miles
- Detour Implementation Date: May 16, 2022
- Anticipated Date Detour to be Lifted: October 2022
- Contractor: Cottle's Asphalt Maintenance
- Current Contract: $19,399,670
View Breezewood to Fulton County detour map (PDF).
- Scope: Bridge replacement
- Traffic Control: Detour
- Construction Timeframe: June - November 2023
- Detour Length:
- Detour Implementation Date: June 6, 2023
- Date Detour Lifted: October 12, 2023
- Contractor: Wen-Brooke Contracting, Inc.
- Current Contract: $425,130
View the Route T-383: Barkley Road Bridge Detour Map (PDF).