Begin Main Content Area

Project Overview

​This project will involve the replacement of the existing slab bridge carrying State Route (S.R.) 405 (Water Street) over Glade Run with a longer bridge.  The traffic signal equipment at the intersection will be replaced, some drainage repairs, ADA ramp upgrades, milling of the existing surface from Main Street to Williams Street, and overlay from Main Street to Williams Street.  Southbound Water Street traffic will be maintained on Williams Street and Green Street while Northbound Water Street traffic will be maintained on Carpenter Street and Williams Street during construction of the bridge.  There will be separate truck detours for access to the industrial areas to the north and west of the borough.

Project Contact

​Design Project Manager

Chris Neidig | cneidig@pa.gov

Phone: 570.368.4391

Community Relations Coordinator 

Dave Thompson | dmthompson@pa.gov

Phone: 570.368.4202

Project Statistics

Contract Cost: $2,300,000

Percentage Complete: 30% Design

Primary Contractor: N/A

Detour Information

​See Resources.