Begin Main Content Area

​Project Overview

Project Description

The purpose of the Potters Mills Gap (PMG) Transportation Project is to improve safety, reduce congestion, and alleviate access concerns along the section of Route 322 from the Centre County/Mifflin County line to west of the Route 322/Route 144 intersection at Potters Mills. Section B04 (the Bridge over SR 322), the first of three sections of the PMG project was completed on September 23, 2015, Section B05 (Sand Mountain Road Interchange at Seven Mountains) was completed on March 30, 2018. The last section, Section B06 (4-Lane Extension and Western Interchange) is currently under construction and is scheduled to be physically complete and fully open to traffic by October 2020.

Project Contacts

Greg Sidorick, Project Manager
814-531-4295 | gsidorick@pa.gov

Brent Lykens, Construction and Traffic Control Questions
814-762-5036 | blykens@pa.gov

Craig Sattesahn, Design Questions
814-765-0678 | csattesahn@pa.gov

Marla Fannin, Community Relations Coordinator
814-765-0423 | mfannin@pa.gov

Project Statistics

Section — B04 Bridge over SR 322

Contractor Notice to Proceed: December 8, 2014

Contract Cost: $1,944,805

% Complete: 100%

Prime Contractor: Jay Fulkroad & Sons of McAlisterville

Section B05 - Sand Mountain Road Interchange

Contractor Notice to Proceed: August 8, 2016

Prime Contractor: Glenn O. Hawbaker, Inc. of State College

Contract Cost: $8,676,545

% Complete: 100%

Section B06 - 4-Lane Extension and Western Interchange

Contractor Notice to Proceed: May 7, 2018

Prime Contractor: Glenn O. Hawbaker, Inc. of State College

Contract Cost: $82,374,064

% Complete: 5%

News Releases

pr265-2018 Potters Mills Gap Update for early December

pr262-2018 Potters Mills Gap Update Through November

pr255-2018 Potter Mills Gap Update Through Mid-November

pr251-2018 Delays Possible Next Week at Potters Mills Project Site

pr244-2018 Potters Mills Project May Have Delays Next Week

pr235-2018 Potters Mills Update Through October

pr221-2018 Potters Mills Update Into mid-October

Potters Mills Update Through September

Potters Mills Update Through Mid-September

  

Detour Information

N/A