​Project Overview

Project Description

The purpose of the Potters Mills Gap (PMG) Transportation Project is to improve safety, reduce congestion, and alleviate access concerns along the section of Route 322 from the Centre County/Mifflin County line to west of the Route 322/Route 144 intersection at Potters Mills. Section B04 (the Bridge over SR 322), the first of three sections of the PMG project was completed on September 23, 2015, Section B05 (Sand Mountain Road Interchange at Seven Mountains) was completed on March 30, 2018. The last section, Section B06 (4-Lane Extension and Western Interchange) is currently under construction and is scheduled to be physically complete and fully open to traffic by October 2020.

Project Contacts

Greg Sidorick, Project Manager
814-531-4295 | gsidorick@pa.gov

Brent Lykens, Construction and Traffic Control Questions
814-762-5036 | blykens@pa.gov

Craig Sattesahn, Design Questions
814-765-0678 | csattesahn@pa.gov

Marla Fannin, Community Relations Coordinator
814-765-0423 | mfannin@pa.gov

Project Statistics

Section — B04 Bridge over SR 322

Contractor Notice to Proceed: December 8, 2014

Contract Cost: $1,944,805

% Complete: 100%

Prime Contractor: Jay Fulkroad & Sons of McAlisterville

Section B05 - Sand Mountain Road Interchange

Contractor Notice to Proceed: August 8, 2016

Prime Contractor: Glenn O. Hawbaker, Inc. of State College

Contract Cost: $8,676,545

% Complete: 100%

Section B06 - 4-Lane Extension and Western Interchange

Contractor Notice to Proceed: May 7, 2018

Prime Contractor: Glenn O. Hawbaker, Inc. of State College

Contract Cost: $82,374,064

% Complete: 85%

News Releases

pr193-2020 Potters Mills Update for Mid-October.pdf

pr183-2020 Potters Mills Update for Early October.pdf

pr170-2020 Potters Mills Update for Late September.pdf

pr111-2020 Potters Mills Reminder for Detour.pdf

pr107-2020 Potters Mills Update for mid-July.pdf

 pr83-2020 Potters Mills Update for Late June.pdf

pr45-2020 Potters Mills Update for Early to mid-May.pdf

pr36-2020 Potters Mills Update for Early to mid-April.pdf