​Project Overview

 

Project Description

 
The purpose of the Potters Mills Gap (PMG) Transportation Project is to improve safety, reduce congestion, and alleviate access concerns along the section of Route 322 from the Centre County/Mifflin County line to west of the Route 322/Route 144 intersection at Potters Mills. Section B04 (the Bridge over SR 322), the first of three sections of the PMG project was completed on September 23, 2015, Section B05 (Sand Mountain Road Interchange at Seven Mountains) was completed on March 30, 2018.  The last section, Section B06(4-Lane Extension and Western Interchange) is currently under construction and is scheduled to be physically complete and fully open to traffic by October 2020.
 

Project Contacts
 
Greg Sidorick / Project Manager
 
814-531-4295  |  gsidorick@pa.gov
 
Brent Lykens / Construction and Traffic Control Questions
 
814-762-5036  |  blykens@pa.gov
 
Craig Sattesahn / Design Questions
 
814-765-0678  csattesahn@pa.gov
 
 
 
Community Relations Coordinator
 
Marla Fannin
 
814-765-0423mfannin@pa.gov
 
 
 

Project Statistics

 
Section - B04 Bridge over SR 322
 
Contractor Notice to Proceed: December 8, 2014
 
Contract Cost: $1,944,805.00
 
% Complete: 100%
 
Prime Contractor: Jay Fulkroad & Sons of McAlisterville
 
 
 
Section B05 - Sand Mountain Road Interchange
 
Contractor Notice to Proceed: August 8, 2016
Prime Contractor: Glenn O. Hawbaker, Inc. of State College
Contract Cost: $8,676,545.00
% Complete: 100%
 
 
Section B06 - 4-Lane Extension and Western Interchange
 
Contractor Notice to Proceed: May 7,  2018
 
Prime Contractor: Glenn O. Hawbaker , Inc.  of State College
 
Contract Cost: $82,374,064.00
 
% Complete: 5%
 
 