Project Overview
Project Description
The purpose of the Potters Mills Gap (PMG) Transportation Project is to improve safety, reduce congestion, and alleviate access concerns along the section of Route 322 from the Centre County/Mifflin County line to west of the Route 322/Route 144 intersection at Potters Mills. Section B04 (the Bridge over SR 322), the first of three sections of the PMG project was completed on September 23, 2015, Section B05 (Sand Mountain Road Interchange at Seven Mountains) was completed on March 30, 2018. The last section, Section B06 (4-Lane Extension and Western Interchange) is currently under construction and is scheduled to be physically complete and fully open to traffic by October 2020.
Project Contacts
Greg Sidorick, Project Manager
814-531-4295
|
gsidorick@pa.gov
Brent Lykens, Construction and Traffic Control Questions
814-762-5036
|
blykens@pa.gov
Craig Sattesahn, Design Questions
814-765-0678
|
csattesahn@pa.gov
Marla Fannin, Community Relations Coordinator
814-765-0423
|
mfannin@pa.gov
Project Statistics
Section — B04 Bridge over SR 322
Contractor Notice to Proceed: December 8, 2014
Contract Cost: $1,944,805
% Complete: 100%
Prime Contractor: Jay Fulkroad & Sons of McAlisterville
Section B05 - Sand Mountain Road Interchange
Contractor Notice to Proceed: August 8, 2016
Prime Contractor: Glenn O. Hawbaker, Inc. of State College
Contract Cost: $10 Million
% Complete: 100%
Section B06 - 4-Lane Extension and Western Interchange
Contractor Notice to Proceed: May 7, 2018
Prime Contractor: Glenn O. Hawbaker, Inc. of State College
Contract Cost: $84 Million
% Complete: 85%
News Releases
pr05-2021 Potters Mills Work to Resume.pdf
pr211-2020 PennDOT Celebrates Near Completion of Potters Mills Gap Project.pdf
pr209-2020 Potters Mills Job to Shut Down for the Winter.pdf
pr193-2020 Potters Mills Update for Mid-October.pdf
pr183-2020 Potters Mills Update for Early October.pdf
pr170-2020 Potters Mills Update for Late September.pdf
pr111-2020 Potters Mills Reminder for Detour.pdf
pr107-2020 Potters Mills Update for mid-July.pdf
pr83-2020 Potters Mills Update for Late June.pdf
pr45-2020 Potters Mills Update for Early to mid-May.pdf
pr36-2020 Potters Mills Update for Early to mid-April.pdf
Detour Information
N/A