Begin Main Content Area

Crawford County - North Perry Street Bridge Replacement Project

North Perry Street Bridge Replacement Project Map

The Pennsylvania Department of Transportation (PennDOT) invites the public to a plans display for superstructure replacement on North Perry Street (Route 2031) Bridge over Thompson Creek in Oil Creek Township, Crawford County. 

Plans call for replacing the concrete box beams, parapets, and deck, and updating the guiderail. Work is expected to occur during the 2020 construction season.

The plans display will be held:

Date: February 3, 2020, to February 13, 2020
Time: 8:30 AM to 4:00 PM – Monday through Thursday
Location: Oil Creek Township Building
127 McKinney Street
Titusville, PA 16345

A detour will be required for this project, which will be 8.5 miles long and uses Thompson Run Road and Route 89. The bridge is expected to be closed for approximately three months.

Contact:

Ken Sanoski, PE., - PennDOT Project Manager, ksanoski@pa.gov, or call 814-678-7078