Begin Main Content Area

Crawford County - Route 408 Bridge Replacement Project

Route408Bridge-19.jpg










The Pennsylvania Department of Transportation (PennDOT) invites the public to a meeting for the replacement of Route 408 (Church Street) Bridge over East Branch Sugar Creek in Troy Township, Crawford County.

The project will include replacing the existing bridge with a precast concrete box culvert. Work will also include a new bridge deck and guide rail.

The public meeting will be held:

Date: Tuesday, March 10, 2020
Time: Presentation at 5:00 PM
Location: Troy Township Building
36431 Bowmaster Road
Centerville, PA 16404

Work is expected to occur in the summer of 2020. The bridge is expected to be closed for three months. 

A detour will be in place during construction. The 19.8-mile detour will include Route 8, Route 27, and Route 428.

Contact:

Ken Sanoski, P.E - PennDOT Project Manager, ksanoski@pa.gov , or call 814-678-7078