Oliver Road Intersection Improvement Project



Project Overview

The Oliver Road Intersection Improvement Project includes the construction of a five-leg roundabout at the intersections of Oliver (Route 4008), Flower, and Hamot (Route 4010) roads in Summit Township, Erie County. 

The intersection safety improvement project was created to address concerns raised by data gathered from 2012 to 2016 and studies conducted in 2019, which showed that crash rates at this intersection were over two times the statewide average for similar roadways and that the intersection geometry contributed to a large percentage of these crashes.

The two-year project will include removal of the existing intersections and construction of roundabout. Additional work includes milling and paving intersecting roads, construction of sidewalks, ADA curb ramps, drainage improvements, environmental mitigation, lighting, vegetation replacement, and pavement markings. 

Work started on June 21, 2021. The construction plan for this project will be organized into seven phases. Different detours will be needed for various phases of the project. 

Work is expected to shutdown for the winter following Phase 3. Temporary pavement markings and traffic control devices will be in place and all detours will be lifted during the winter months.

The roundabout is expected to be fully opened to traffic in July 2022.

Oliver Road Roundabout2.jpg

Project Phases

Phase 1A
Will include the construction of the offline portion of the roundabout and the offline portion of the new alignments of Flower and Hamot roads. Work also includes new roadway approaches, drainage, sidewalks, and concrete islands. Work is expected to be completed in the 2021 construction season.

Phase 1B
Will focus on the Hamot Road north approach to the new roadway and the removal of the unused portion of Hamot Road. Temporary lanes will be constructed for two-lane traffic on Hamot Road. Additional drainage work will also be done. Traffic on Hamot Road will be detoured using Route 19 (Peach Street) and Hershey Road.  The detour is expected to be in place mid-April 2022. Work is expected to take approximately eight days.

Phase 2A
Will include the construction of the approach on Oliver Road, as well as drainage, sidewalks, and concrete islands. Traffic will use the temporary lanes on Hamot Road. Work is expected to take approximately 12 days to complete.

Phase 2B
Will include the tie-in between Oliver Road approach and the new roadway. Work will also include the removal of a portion of the existing Oliver Road as well as drainage and sidewalks. Oliver Road traffic will be detoured using Hamot Road, Hershey Road, and Route 19. Work is expected to take approximately 11 days.

Phase 3
Will include the construction of the tie-in between Flower Road approach and new roadway. Work will also include the removal of a portion of the existing Flower Road as well as drainage and sidewalks. Flower Road traffic will be detoured using the Oliver Road, Dunn Valley Road (Route 4013), and Reichert Road (Route 4013). Work is expected to take approximately 15 days. 

Phase 4
Work will include removing another portion of the existing Oliver Road approach and construction of the tie-in between the Oliver Road and the new roadway. Traffic on Oliver Road and Hamot Road will be detoured using Flower Road, Reichert Road, and Dunn Valley Road. Work is expected to take approximately 14 days.

Phase 5
Will include constructing a tie-in between the south Hamot Road approach and the new roadway. Work will require varying detours between Oliver Road and Hamot Road.  Drivers should be alert for changing traffic patterns and detour signs. Work is expected to take approximately 10 days to complete. 

Phase 6
Will include constructing the central island including the truck apron, curbs and landscaping. Work is expected to take approximately 28 days to complete. 

Phase 7
Will include milling and paving the final surface for the roundabout lanes, as well as sign installation. 

Oliver Rd Roundabout2 7-9-21.JPG

Project Updates


11-10-21

Work on the project is wrapping up for the 2021 construction season. The project will restart on Phase 1B in April 2022, weather permitting. 

6-9-21

Construction at the intersection improvement project at the intersection of Oliver Road, Flower Road, and Hamot Road in Summit Township, Erie County is scheduled to begin June 21, 2021 weather permitting and is expected to be completed by July 2022.

Motorists may encounter lane restrictions with traffic controlled by flaggers. Drivers should be alert for traffic pattern shifts and lane restrictions and should anticipate travel delays during active work hours.